OPTIMASI PERAKITAN LIFT MENGGUNAKAN METODE BINARY INTEGER PROGRAMMING

Sofi Ainun Sadikin, . (2021) OPTIMASI PERAKITAN LIFT MENGGUNAKAN METODE BINARY INTEGER PROGRAMMING. Skripsi thesis, Universitas Pembangunan Nasional Veteran Jakarta.

[img] Text
ABSTRAK.pdf

Download (12kB)
[img] Text
AWAL.pdf

Download (349kB)
[img] Text
BAB 1.pdf

Download (156kB)
[img] Text
BAB 2.pdf
Restricted to Repository UPNVJ Only

Download (328kB)
[img] Text
BAB 3.pdf
Restricted to Repository UPNVJ Only

Download (123kB)
[img] Text
BAB 4.pdf
Restricted to Repository UPNVJ Only

Download (555kB)
[img] Text
BAB 5.pdf

Download (72kB)
[img] Text
DAFTAR PUSTAKA.pdf

Download (78kB)
[img] Text
RIWAYAT HIDUP.pdf
Restricted to Repository UPNVJ Only

Download (86kB)
[img] Text
LAMPIRAN.pdf
Restricted to Repository UPNVJ Only

Download (774kB)
[img] Text
ARTIKEL KI.pdf
Restricted to Repository staff only

Download (307kB)

Abstract

PT. XYZ is a sub contractor company operated in the installation of lift. While company run a project, they often experience problems like material requirements that are not on time. This occur because one of the workstations experienced a delay in the completion of the assembly. Therefore, the overall workload between workstations becomes significantly unbalanced and makes the project delayed. Based on these problems, it is necessary to create a new workstation system that intends to add operators to pursue delays in completion with the approach of line balancing method. But the addition of the operator depends on the value of the penalty delay of each employment contract. The line balancing process is assisted by the binary integer programming method to group the working elements of the precedence diagram. The workstation in actual condition consists of 30 workstations and in the proposed condition consists of 35 workstations. The number of workstations in the proposed conditions can provide greater efficiency and balance than in actual conditions. The line efficiency value is 82.50%, the balance delay is 17.50%, the idle time is 960.34 minutes, and the smoothness index is 224.50 in the proposed condition. Omega Apartment Project has been completed and experienced delays of 14 days. With the proposed system between workstations, delay condition is reduced to 8 days. Although the delay is not reduced to zero day, the proposed system between workstations conditions can be used to anticipate similar events in the future.

Item Type: Thesis (Skripsi)
Additional Information: [No. Panggil : 1710312009] [Pembimbing 1 : Donny Montreano] [Pembimbing 2 : Akhmad Nidhomuz Zaman] [Penguji 1 : Reda Rizal] [Penguji 2 : Santika Sari]
Uncontrolled Keywords: Line Balancing, Binary Integer Programming, Lift Installation Project
Subjects: T Technology > TA Engineering (General). Civil engineering (General)
T Technology > TH Building construction
T Technology > TJ Mechanical engineering and machinery
T Technology > TK Electrical engineering. Electronics Nuclear engineering
T Technology > TS Manufactures
Divisions: Fakultas Teknik > Program Studi Teknik Industri (S1)
Depositing User: Sofi Ainun Sadikin
Date Deposited: 22 Sep 2021 05:45
Last Modified: 22 Sep 2021 05:45
URI: http://repository.upnvj.ac.id/id/eprint/11569