Marcellio Kebayakenta Maha, . (2021) OPTIMALISASI WAKTU DAN BIAYA PROYEK RENOVASI RUMAH OLEH PT. XYZ DENGAN METODE CRASHING. Skripsi thesis, Universitas Pembangunan Nasional Veteran Jakarta.
Text
ABSTRAK.pdf Download (10kB) |
|
Text
AWAL.pdf Download (492kB) |
|
Text
BAB 1.pdf Download (90kB) |
|
Text
BAB 2.pdf Restricted to Repository UPNVJ Only Download (420kB) |
|
Text
BAB 3.pdf Restricted to Repository UPNVJ Only Download (104kB) |
|
Text
BAB 4.pdf Restricted to Repository UPNVJ Only Download (677kB) |
|
Text
BAB 5.pdf Download (77kB) |
|
Text
DAFTAR PUSTAKA.pdf Download (160kB) |
|
Text
RIWAYAT HIDUP.pdf Restricted to Repository UPNVJ Only Download (17kB) |
|
Text
LAMPIRAN.pdf Restricted to Repository UPNVJ Only Download (375kB) |
|
Text
HASIL PLAGIARISME.pdf Restricted to Repository staff only Download (12MB) |
|
Text
ARTIKEL KI.pdf Restricted to Repository staff only Download (369kB) |
Abstract
Every project has a deadline, which means that the project must be completed before or right on the specified schedule. But in reality, in carrying out a project there are uncertain events that result in delays. This study uses a house renovation object that takes 87 days. This project experienced a delay of 8 days so that a project acceleration was needed, besides the objectives of this study were to identify critical activities, calculate the chances of project success, calculate time and cost after acceleration, and determine optimal time and cost after acceleration to overcome delays. The methods used are; CPM, PERT, and Crashing. By using the CPM method, 29 critical activities can be identified, then with the PERT method, the probability of project success is 82.89%, and through crashing the addition of 2 hours of overtime work can cut time to 77 days with a total cost of Rp. 265,980,986, while the addition of 3 hours of overtime can reduce the time to 74 days with a total cost of Rp. 274.111,080. The optimal alternative in this research is the addition of 2 hours of overtime work by accelerating 10 days with a total cost slope of Rp. 600,691.
Item Type: | Thesis (Skripsi) |
---|---|
Additional Information: | [No. Panggil: 1810312032] [Pembimbing: Muhamad As'adi} [Penguji 1: Donny Montreano] [Penguji 2: Santika Sari] |
Uncontrolled Keywords: | CPM, Crashing, Home Renovation, Optimization, PERT, Project |
Subjects: | T Technology > T Technology (General) T Technology > TH Building construction |
Divisions: | Fakultas Teknik > Program Studi Teknik Industri (S1) |
Depositing User: | Marcellio Kebayakenta Maha |
Date Deposited: | 09 Feb 2022 04:35 |
Last Modified: | 09 Feb 2022 04:35 |
URI: | http://repository.upnvj.ac.id/id/eprint/16345 |
Actions (login required)
View Item |