Pengendalian Durasi Proyek Enterprise Resource Planning Berbasis Kuantifikasi Dinamika Aliran Proses Bisnis (Studi Kasus: Proyek PT. Synova Tech Solutions)

Raidha Karimah, . (2026) Pengendalian Durasi Proyek Enterprise Resource Planning Berbasis Kuantifikasi Dinamika Aliran Proses Bisnis (Studi Kasus: Proyek PT. Synova Tech Solutions). Skripsi thesis, Universitas Pembangunan Nasional Veteran Jakarta.

[img] Text
ABSTRAK.pdf

Download (238kB)
[img] Text
AWAL.pdf

Download (754kB)
[img] Text
BAB 1.pdf
Restricted to Repository UPNVJ Only

Download (404kB)
[img] Text
BAB 2.pdf
Restricted to Repository UPNVJ Only

Download (1MB)
[img] Text
BAB 3.pdf
Restricted to Repository UPNVJ Only

Download (456kB)
[img] Text
BAB 4.pdf
Restricted to Repository UPNVJ Only

Download (1MB)
[img] Text
BAB 5.pdf

Download (237kB)
[img] Text
DAFTAR PUSTAKA.pdf

Download (253kB)
[img] Text
RIWAYAT HIDUP.pdf
Restricted to Repository UPNVJ Only

Download (174kB)
[img] Text
LAMPIRAN.pdf
Restricted to Repository UPNVJ Only

Download (2MB)
[img] Text
HASIL PLAGIARISME.pdf
Restricted to Repository staff only

Download (18MB)
[img] Text
ARTIKEL KI.pdf
Restricted to Repository staff only

Download (627kB)

Abstract

PT Synova Tech Solutions, an Epicor Kinetic ERP implementation provider, frequently experiences project delays. This research evaluates three ERP implementation projects, namely Atlas, Orbit, and Bridge (2024-2025), using process mining with PM4Py (process discovery, conformance checking, and process enhancement), followed by the Fuzzy PERT method to assess delay risk and formulate acceleration strategies. Process mining results show five process phases with high conformance (fitness 0.860 to 0.981), with the largest delays occurring in the Training & Testing and Deployment phases. Orbit was the longest running project at 333 days. Fuzzy PERT results indicate low probabilities of on target completion, at 33.5% for Atlas, 25.4% for Bridge, and 17.6% for Orbit. Acceleration simulations on critical activities produced durations of 105.53 days for Atlas, 119.80 days for Bridge, and 143.57 days for Orbit, demonstrating that this method effectively evaluates and optimizes project completion based on actual data.

Item Type: Thesis (Skripsi)
Additional Information: [No.Panggil: 2210312074] [Pembimbing: Yulizar Widiatama] [Penguji 1: Donny Montreano] [Penguji 2: Harditriyono Putra]
Uncontrolled Keywords: Process Mining for Python, Fuzzy PERT, ERP Implementation
Subjects: T Technology > T Technology (General)
T Technology > TA Engineering (General). Civil engineering (General)
T Technology > TS Manufactures
Divisions: Fakultas Teknik > Program Studi Teknik Industri (S1)
Depositing User: RAIDHA KARIMAH
Date Deposited: 29 Aug 2026 02:52
Last Modified: 29 Aug 2026 02:52
URI: http://repository.upnvj.ac.id/id/eprint/53102